27th PDWP

Energy Sector

 
2x55 MW (Gross) Coal Fired Power Plant at Sundar Industrial Estate Lahore.  
Cost: US$. 322.360 million | Status: Deffered | ADP No. 2176  (New)  
   

Literacy Sector

 
Non-Formal Education Promotion Project with Japan International Cooperation Agency (JICA).   
Cost: PKR  191.049 million | Status: Approved | ADP No.415  (On-going)  
   
Third Party Evaluation of Literacy Projects.(PC-II)  
Cost: PKR  50.000 million | Status: Approved | ADP No.424  (New)  
   

Education Sector

 
Extension of Building of Bahadur Sub-Campus of BZU at Layyah.  
Cost: PKR  354.672 million | Status: Approved | ADP No. 278 (New)   
   

Health Sector

 
Construction of Surgical Tower at Mayo Hospital, Lahore. (Revised)  
Cost: PKR  3,656.294 million | Status:  Deferred | ADP No. 598  (On-going)  
   

Emergency Services Sector

 
Establishment of Expansion of Emergency Service to Tehsils (Phase-II)  
Cost: PKR 1,090.009 million | Status: Approved | ADP No. 2468  (New)  
   

Urban Development Sector

 
Punjab Water & Sanitation Academy Lahore.  
Cost: PKR  673.251 million | Status: Approved | ADP No.2195  (On-going)  
   

Public Buildings Sector

 
Construction of Purpose Built Building for Archives Wing of S&GAD in Punjab Civil Secretariat, Lahore.  
Cost: PKR  277.972 million | Status: Approved   
   

Roads Sector

 
Dualization of Samundri-Rajana-Toba Tek Singh Road, length=49 Km, Faisalabad / T.T. Singh.  
Cost: PKR 3,178.145 million | Status: Approved | ADP No. 1513  (New)  
   
Widening / Improvement of Jourian Chakri Road Including Missing Link Kachi Jourian to Choutra, length 22.20 km, District Rawalpindi.  
Cost: PKR 263.936 million | Status: Approved   
   
Construction of Bridge on River Ravi at Qutab Shahana  in District Sahiwal.  
Cost: PKR 1,799.815 million | Status: Approved | ADP No. 1319  (On-going)  
   
Widening / Improvement of Bahawalnagar-Haroonabad Road length:53.00 km District Bahawalnagar. (Revised)   
Cost: PKR 1,502.315 million | Status: Approved | ADP No. 1354  (On-going)  
   
Dual Carriageway with Green Belt and Lights from Cantt Baker to Railway Station via Chowk Munir Shaheed (length:2.65 km) District Bahawalpur.  
Cost: PKR 513.241 million | Status: Approved   
   

Irrigation Sector

 
Construction of Mahota Dam, Rawalpindi.  
Cost: PKR  1861.985 million | Status: Approved | ADP No.1748  (New)  
   
Restoration of J-Head Spur RD. 167+000 of link No.1 Tehsil D.G. Khan.  
Cost: PKR  147.247 million | Status: Approved   
   
Restoration of J-Head Super RD. 165+000 of Link No.1 Tehsil D.G. Khan.  
Cost: PKR 278.578 million | Status: Approved  
   
Management of Hill Torrents in Irrigation Zone, D.G. Khan-Sori Lund, Vidore, Mithawan, Kaha & Chachar (Kaha Hill Torrent).  
Cost: PKR  968.713 million | Status: Approved | ADP No.1709  (On-going)