36th PDWP

PPH Sector

Water Supply Scheme Sadiqabad, Tehsil Sadiqabad District Rahim Yar Khan
Cost: PKR 711.538 million | Status: Deferred                            
 

US Sector

Upgrading of Mechanical System for Sewerage and Drainage Services in Gujranwala
Cost: PKR 1,240.080 million | Status: Approved
 

Transport Sector

Extension in gestation period for Clearing pending liabilities of 4-stroke CNG Rickshaw scheme under the Chief Minister Green Fund Programme”
Cost: PKR Issue million | Status: Approved
 
Construction of Bus Rapid Transit System along Ferozepur Road, Package-III: Qartaba Chowk to M.A.O College (Elevated Section-2.5 km).(Revised)
Cost: PKR 6,244.924 million | Status: Approved
 

Energy Sector

Acquisition of Land for Establishment of 2x660 MW Coal Based Power Plant near Qadirabad in District Sahiwal
Cost: PKR 2,162.000 million | Status: Deferred
 

Agriculture Sector

Supply Chain Improvement of Selected Agriculture and Livestock Products                          
Cost: PKR 2,414.235 million | Status: Approved | ADP No. 1372 (on-going)
 
Promotion of Pulses Cultivation in Punjab
Cost: PKR 148.790 million | Status: Approved
 

EW&F Sector

Feasibility Study Regarding Development of Strategic and Bankable Investment Proposal for Wildlife Park Bansra Gali Murree (PC-II)
Cost: PKR 12.000 million | Status: Deferred | ADP No. 1403 (New)
 
Feasibility Study Regarding Development of Strategic and Bankable Investment Proposal for Lal Suhanra National Park, Bahawalpur and Zoo Safari, Lahore. (PC-II)
Cost: PKR 20.000 million | Status: Deferred
 

Roads Sector

Construction of Road Bridge between District Mianwali and District Attock (Revised)
Cost: PKR 1,784.648 million | Status: Approved | ADP No. 715 (on-going)
 
Widening / Improvement of Shorkot Pattan Road Linking Garh Maharaja, length 8.30 km
Cost: PKR 210.637 million | Status: Approved | ADP No. Distt Dev. Prog. (696)
 
Rehabilitation / Improvement / Widening of Dual Carriageway Between Khushab to Jauharabad Road (Art:2) km No. 214.60 To Km 222.25 length (7.65) km in District Khushab
Cost: PKR 670.931 million | Status: Approved
 

Industries Sector

Acquisition of Land for Establishment of Quaid-e-Azam Apparel Park (previously Garment industrial zone) District Sheikhupura (Revised)
Cost: PKR 3,315.668 million | Status: Approved | ADP No. Ex-Agenda