Irrigation Sector |
Construction of Nutkani Flood Carrying Channel from RD.0+000- 21+000 in District D.G. Khan |
Cost: PKR 889.152 million | Status: Approved | ADP No.1764 (New) |
UD Sector |
Comprehensive water Supply Scheme for Gulraiz, Dhoke Choudhrian, Morgah, Kotha Kalan & Neighbouring Colonies, Rawalpindi |
Cost: PKR 539.788 million | Status: Approved | ADP No. 2241 (New) |
Roads Sector |
Dualization of Muridke Narowal Road from 0.00 to 41.50 km in District Sheikhupura length=41.50 km District Sheikhupura. (Revised) |
Cost: PKR 2,723.989 million | Status: Approved | ADP No. 1304 (on-going) |
Hiring of Consultant for Preparation of TOR’s / Bidding Documents for International Bidding Regarding Topographic Survey and Geotechnical Studies for Land Sliding Zonization of Murree Hill Area Mainly Located Between Old Rawalpindi-Murree Road and Islamabad Murree Expressway, in Murree. (Amended PC-II) |
Cost: PKR 2.785 million | Status: Approved | ADP No. 2153 (on-going) |
RP Sector |
Tribal Area Development Project (TADP) |
Cost: PKR 3,381.00 million | Status: Approved | ADP No. 1176 (on-going) |
Change of executing agency regarding scheme titled “Widening and Improvement of road from Tailwala to Mithra (24 kms)” under CM Cholistan Development Package. (Position Paper) |
Cost: PKR Cleared million | Status: Cleared |