The PDWP Approved Twelve Development Schemes of Various Development Sectors

Monday, April 13, 2015

The Provincial Development Working Party Punjab approved twelve development schemes of various development Sectors with an estimated cost of PKR. 14,780.273 Million.   

These schemes were approved in the 41th meeting of Provincial Development Working Party (PDWP) of current fiscal year 2014-15 presided over by the Punjab Chairman P&D Board Muhammad Irfan Elahi. Provincial Secretary P&D Waseem Ajmal Chaudhary, Members of the Planning & Development Board, Provincial Secretary concerned and other senior representatives of the relevant Provincial Departments also attended the meeting.

According to Spokesman for P&DD, the approved development schemes included:

  • Engagement of Transaction Advisors for Preparation of Complete Project Proposal and Tendering of PPP Project “Outsourcing Services for Operations & Maintenance of Sports Infrastructure Facilities in Punjab” (PC-II) at the cost of PKR. 25.805 Million
  • Establishment of Sub Campus of University of Agriculture, Faisalabad at Depalpur, District Okara at the cost of PKR. 625.729 Million
  • Remodelling/rehabilitation of Inescapable Flood Works (RIFW-I) in Punjab Irrigation Department (Phase-I) at the cost of PKR. 349.251 Million
  • Preparation of Water Quality Survey & Sewerage Master Plan/Development Plan of Districts, Tehsil and Urban Area. (PC-II) at the cost of PKR. 19.983 Million
  • Sewerage System from Larech Colony to Gulshan-e-Ravi Lahore at the cost of PKR. 6978.635 Million
  • Area Development Scheme No.II, Sheikhupura at the cost of PKR. 456.108 Million
  • Master Planning of Water Supply, Sewerage & Drainage System i/c Consumers Surveyand Up-Gradation of Billing System of WASA Multan (PC-II) at the cost of PKR. 153.648 Million
  • Upgradation of Government General Hospital Ghulam Muhammad Abad, Faisalabad (Revised) at the cost of PKR. 986.450 Million
  • Construction of Surgical Tower at Mayo Hospital, Lahore (Revised) at the cost of PKR. 2678.104 Million
  • Establishment of State of the Art Trauma Centre at Kallar Kahar District Chakwal (Revised) at the cost of RPR.. 260.373 Million
  • Widening/Improvement of Road Sheikhupura Sargodha Road km No. 37 to 49.56 to 61.30 and 71.60 to 83.30 length: 20.90 km in District Sheikhupura (Revised) at the cost of PKR. 1079.601 Million
  • Dualization of Lahore Jaranwala Road from Mandi Faizabad to Magtanwala length: 15.40 km in District Nankana Sahib (Revised) at the cost of PKR. 1166.631 Million